|
![]()
![]() ![]()
![]() ![]() ![]() The Robotic Pipe Layer
The WCS Robotic Pipe Layer machine
is innovative because it greatly
increases the productivity of how
pipe is laid throughout the world:
§
It has an immediate, positive
economic impact on ROI
§
It is the only system in the world
that can construct curved sewers
saving and reducing Manholes, land
purchases, failures, maintenance and
materials
§
It uses a new a more productive
process for laying pipe while more
than doubling the speed.
§
It is a major advancement in
excavation safety lowering insurance
premiums
§
It substantially increases the
degree of competitive pressure.
§
Companies that don’t use the WCS
Robotic Pipe Layer will be
negatively impacted.
The installation of underground pipe
or conduit is currently a manual,
labor-intensive process that
combines physically difficult work
for multiple laborers. The inherent
dangers of work below ground level
are vast and many. These injuries
and deaths include cave-ins and
accidental collision between
humans and the excavator. To make
matters worse, experienced operators
with the skill set needed to lay
large diameter pipe successfully are
very scarce.
Assuming that the engineering site
design and layout work is complete,
the current method includes eight
steps for each section of pipe:
·
excavation of the basic trench into
which the pipe will be placed,
·
excavation of trench walls to
prevent cave-in of the sidewalls of
the trench,
·
establishment of the baseline level
for the pipe section,
·
placement and leveling of the rock
substrate upon which the pipe will
be laid,
·
placement and leveling of the pipe,
·
joining of the pipe to the
neighboring section of pipe,
·
placement of the rock cover for the
pipe, and
·
backfilling of the trench.
The cycle is then repeated for the
next section of pipe.
As noted above, the work is
dangerous as well as difficult. Even
though the Occupational Health and
Safety Administration (OSHA) has
extensive safety requirements
applicable to the placement of
underground pipe, the National
Institute for Occupational Safety
and Health (NIOSH) reports that
there are typically more than 1000
lost-time injuries in these trenches
in the US every year caused by
cave-ins, falling pipes and
back-fill materials, or impacts with
heavy equipment. More than 50 of
these injuries typically result in
death each year in the
Note: The
specific numbers quoted here can be
verified and expanded upon at
www.cdc.gov/mmwr/preview/mmwrhtml/mm5315a2.htm;
for more general information
regarding trenching safety see
www.cdc.gov/niosh/topics/trenching/.
By using WCS Robotic Pipe Layer to
place the pipe, the speed and
accuracy of the pipe laying process
is enhanced and workers are removed
from the dangerous below-ground
environment. This combination of
improvements increases the
efficiency of the overall process,
reduces lost-time injuries, and
lowers the cost of insurance. The
economic impact is significant: we
project an increase in the profit
margin in excess of 40%. Contractors
placing underground conduits will
see that Robotic Pipe Layer will
typically pay for itself in the
first three months of use.
Specific Customer NeedsThe foremost concern of any excavation company is the safety of its employees. Even when the utmost care is taken, underground excavation remains a dangerous line of work. By using Robotic Pipe Layer, companies will eliminate the number one safety concern at every excavation site: personnel in the trench. Excavation companies pay exorbitant insurance premiums because of the danger involved in having personnel in the trench. As a secondary benefit, Robotic Pipe Layer will also reduce the cost of insurance. While the Robotic Pipe Layer lays the pipe in the current trench, the excavator operator can be digging the trench for the next section of pipe. This provides the multi-tasking that increases productivity dramatically
Applications
and Specific Uses
Two versions of the Robotic Pipe
Layer robotic pipe layer will
eventially be available: one for
plastic pipe and one for reinforced
concrete pipe. Plastic pipe is used
mainly for sanitary sewer, city
water, and storm sewer while
reinforced concrete pipe is used for
storm sewer. Plastic pipe is used as
part of the plumbing scheme wherever
buildings (homes, offices, etc.) are
being erected. Concrete pipe is used
for drainage from road beds and
retention ponds.
Value Proposition to Customer· Test 1: Illustrates the savings per foot of pipe laid with a variety of pipe sizes on a Daily Basis. · Test 2: Illustrates the annual increase in profits with a variety of pipe sizes. · Test 3: Illustrates the dollar savings between the conventional method and the Robotic Pipe Layer in the following scenarios: 1. With an increase in the rate of conduit laid between 0 and 100% (Note: 100% is twice the normal rate.) 2. With an annual usage rate of between 50 and 250 days per year. For complete details, see Attachments P-R. Competitive AdvantageThere are no direct automated or mechanized competitors to the Robotic Pipe Layer: this is breakthrough technology. The closest competitors are teams of experienced pipe layers using a combination of heavy equipment to lay pipe. The WCS main competitive advantage offered by Robotic Pipe Layer is that it will double the productivity of the average crew and thereby increase profits dramatically. Robotic Pipe Layer also improves safety by eliminating the need for personnel to be below grade. It also improves the efficiency of the crew because the excavator operator can be digging the next section of the trench while the Robotic Pipe Layer operator lays the pipe. Robotic Pipe Layer will also reduce the size of the crew involved in laying pipe. Intellectual Property Protection (Patent # 7607863)WCS Inc will have a patent that will prevent the other manufacturers from manufacturing a machine that is similar to the Robotic Pipe Layer. The patent has been awarded number 7607863. This will provide a micro monopoly market for WCS to sell into for the life of the patent, which will last approximately through 2026. Market & Competitive AnalysisMarket AssessmentNational Market Assessment
The placement of underground pipe
and conduit of various sorts
accounts for $40 billion or 4% of
the annual It should be noted that these projections were made before the passage of the economic stimulus plan which includes financial support for extensive infrastructural repair, replacement and extension. Many of these projects are likely to involve extensive underground pipeline or conduit installations. The projected growth for the related sectors are, therefore, probably somewhat conservative for 2009 and beyond.
Note: Data is from FMI, a firm which
provides management consulting and
investment banking for the worldwide
construction industry. Projections
made in late 2008.
|
FOR INFO CALL
(317) 590-8251